Shah Wa Arous Dam

Shah Wa Arous Dam

The main constraint on developing sustainable large scale agriculture in Afghanistan is inadequate water resource, although total water availability is substantial annually. Therefore, development and regulation of the rivers & streams are necessary in order to facilitate water supply throughout the year, mitigate flood damages, generate hydro-power, domestic supply, etc. Shah-Wa-Arus multipurpose Project is one of the suitable projects based on performed prefeasibility & feasibility studies.


Status of Project: In Progress

Project Highlights

Role of Parhoon Tarh: EPC Contractor as member of Tablieh-Parhoon Tarh J.V.
Client: Afghanistan-Ministry Of Energy & Water
Consultant Engineer: Alborz Sazeh Consultant Engineers
Location: Afghanistan-Kabul
Project Cost: 48 million USD
Project Duration: 55 Months

 

Featured Images

Project Volumes

Dam Concrete Volume: 333,000 m3
Excavation Volume in Rock: 80,000 m3
Access Road Length: 6 Km

Project Specification

Type of Dam: RCC (Roller Compacted Concrete)
Dam Crest Length: 303 m
Type of Spillway: Free Spillway on Dam Crest
Annual Production: 3.60 GWH/year

Project Goals

  • Agricultural land extension of 2,800 hectares Flood control and prevention of resulting damages | Power production of 1.2 MW
  • Increasing the groundwater level

Project Stakeholders

post

Rais Ali Delvari Dam

Rais Ali Delvari Dam

Rais Ali Delvari dam had been constructed on Shapur river, 73 km to north of Bushehr. This project with objectives of water regulation, irrigation, flood control and, power generation was managed by this company.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Managing Contractor
Client: Fars Regional Water Company
Consultant Engineer: Mahab Ghods Consulting Engineers
Location: Iran- Bushehr Province
Project Cost: 35 million USD (Main Contract) 1 million USD (Parhoon Tarh Portion)
Project Duration: 46 months

 

Featured Images

Project Volumes

Dam Concrete for Dam Structure: 220,000 m3
Concrete for Spillway: 30,000 m3
Drilling and Grouting: 100,000 m (Curtain wall)

Project Specification

Type of Dam: Double Arc Concrete
Length at Crown: 240 m
Height from Base: 112 m

Project Goals

  • Agricultural land extension of 19,500 hectares
  • Flood control and prevention of resulting damages
  • Energy production of 96 GWH

Project Stakeholders